Due to unforeseen circumstances ALL contact to “The Scarlet Pimpernel” is suspended. In future constituents will need to apply direct to the “Middlesbrough Town Hall Prospective MP Barn Dancing Extravaganza” Ladies & Gentlemen please take your places for the next dance led by Ray Mallon – Musical Chairs. All participants left without a chair or good enough spin story of why they should be elected MP for Middlesbrough will be removed from the floor. Let the dancing on the ice of spin begin…
Post Reply
User avatar
BoroBot
Site Admin
Posts: 1128
Joined: Wed Dec 22, 2010 8:58 pm

Teessside: Strike a Light

Post by BoroBot »

Have you got a light boy? - time to call
"Inferno Man"
aka The Man in Red:- The Scarlet Pimpernell - MP for Paris
Stuart "I spend Fridays in Middlesbrough visiting the sink Estates trouble shooting" Bell
New delay for SSI Redcar steel plant
Dec 21 2011
Mike Hughes, Evening Gazette

STEEL giant SSI has been forced to delay the restart of its Redcar blast furnace for a second time.
The iconic date was originnally going to be December 8 - but that was too tight a deadline and as more remedial work on the blast furnace was identified, the company committed itself to January 6.
But now a combination of bad weather, union action and the ongping enormous workload means the company cannot commit to a new date.
Phil Dryden, Chief Executive of SSI UK said: “Following a review of the restart programme, I wanted to give this update at the earliest opportunity.
“We are disappointed that we have not met our target date for completing the work at the blastfurnace, but as I have emphasised before, we set ourselves a challenging target and did not build any flex or margin into the programme to cater for the issues which have brought about this delay.
"On a positive note, the rest of the elements of the restart programme are on target including work on all the other parts of the manufacturing assets, the recruitment programme and the procurement of raw materials.
"I appreciate very much the support shown to us, and I remain confident that we will have a successful start up to the operations in the New Year”.
The company has always said the recruitment programme was unaffected by the latest change.
Under enormous pressure from Teesside businesses desperate for a surge in the local economy, the deadlines were always going to be tough, with work across such a vast area of plant to be refurbished and checked.
Read More http://www.gazettelive.co.uk/news/teess ... z1hEve9ltH
User avatar
BoroBot
Site Admin
Posts: 1128
Joined: Wed Dec 22, 2010 8:58 pm

Re: Teessside: Strike a Light

Post by BoroBot »

THE restart of steel production at SSI is now only weeks away after yesterday’s breakthrough announcement.
After two false starts, bosses at the Redcar site said the “finishing line is now in sight” after four massive stoves were lit in preparation for firing up the blast furnace.
Read More http://www.gazettelive.co.uk/news/teess ... z1l8iUIqrT